MMSD Brown Deer Road Construction

Update August 16, 2022- Village staff was notified by the Milwaukee Metropolitan Sewerage District that it will be installing a new sanitary sewer in Brown Deer Road between Regent Road and the railroad tracks beginning in September 2022.  During the first two stages of work between September 6 and December 5, Brown Deer Road and Regent Road is anticipated to remain open to through traffic.  During phases 3 and 4 (December through early February), it is anticipated that the intersection of Brown Deer and Regent Roads will be completely closed to all through traffic.  Detours will be in place to route through traffic around the construction.  Fox Point Village staff has already informed MMSD that the detours should not be Dean, Bradley or Calumet Roads.  For more information, please refer to the attached MMSD informational flyer HERE.

Construction Schedule:

Brown Deer Preliminary Schedule