2017 Road Reconstruction and Utility Project Update

Update (10/18/2017): Work has progressed along Navajo and Seneca as well as Lake Drive with significant headway since the last update on October 5. The first layer of asphalt (binder course) was placed on Seneca on October 17 which is a welcome sight. More work remains to be done and the following update assumes no weather delays:

  • October 19 – Navajo Road will be milled
  • October 23-25 – Driveway preparation activities, subgrade repairs and removal and backfilling of any undesirable soils will be performed along Navajo Road
  • October 26-27 – Fine grade the road and driveways along Navajo Road
  • October 30 – November 3 – pave all driveways, place the first and second lifts (binder and surface course, respectively) on Navajo Road and second lift on Seneca Road
  • Week of November 6 – place stone shoulder along the edge of both roads
  • Week of November 13 (still tentative) – perform final landscape restoration activities

In addition to the work on Navajo and Seneca Roads, the water service laterals have been installed along Lake Drive. The work remaining in this area includes backfilling the excavations, performing landscape restoration activities and completing the internal plumbing. It is anticipated that this work will be completed in the next couple of weeks.

Please note that the contractor will likely need to return to the site next spring to touch up the landscaped areas where vegetation does not become established.

 

Also, during construction activities, please place your leaves roadside as you normally have with one exception – keep the leaves a couple of feet off the shoulder of the road so that construction activities are not impacted. Our crews will continue to vacuum the leaves as normal and will be watching the construction schedule closely so that we can stay ahead of the contractor.

 

As always, should you have any questions, feel free to contact Scott Brandmeier, Director of Public Works, at sbrandmeier@villageoffoxpoint.com or 414-351-8900. Thank you again for your patience during this construction season.

Additional Info...
Facebook Twitter Google Plus Email

Other News in Home

2018 Executive Budget Released

Posted on: October 20, 2017
Trick or Treat

Fox Point Trick or Treat

Posted on: October 20, 2017

Assessment Information Available

Posted on: September 7, 2017